Construction Schedule
3/30/20 – 5/30/20
- Install components of Erosion Control Plan
- Sediment control log
- Swale installation
- Sediment basin and vehicle track control
- Dig retention/detention ponds
- Utilities installation
- Run electrical, natural gas and water into site
- Berm installation
- Access road installation
- Landscape installation
- Grading of batch plant area
- Install gravel plant components
6/1/20 – 8/1/20
- Install foundations for batch plant and cold storage buildings
- Utilities install for batch plant building
- Natural gas
- Electrical
- Septic
- Potable water
- Assemble batch plant
- Construct batch plant building
- Construct cold storage building
- CO RD 54G improvements (notification of exact schedule to be sent to neighbors prior)
8/1/20 – 10/1/20
- Final touches to prepare for operation
*subject to change as project progresses.
Update
LRM will start operating on site the week of March 30th under Development Construction Permit 20-DCP0005.
Construction activities for the Permit will consist of clearing and grubbing existing vegetation from the construction site, construction of the perimeter berms, access roads, ditch crossings; rough grading of the batch plant area and construction of the water management pond; erection of the batch plant and supporting building and facilities; finish grading, install concrete, asphalt, sod, seeding and general landscaping.
Please direct any questions to: laportecomments@lrmconcrete.com
Laporte Pit Quarterly Briefing
Tri-Fold:
When: January 30th, 2020 @ 6pm
Where: WFCWD Building 2711 N Overland Tr., Laporte, CO 80535
Click the links below for Previous Meeting details and literature
Click below to View the Landscape Plan
Questions? Comments? Contact us directly at LaporteComments@LRMconcrete.com