Construction Schedule
Loveland Ready Mix Concrete will continue onsite construction operations under Development Construction Permit 20-DCP0005 and Building Permits 20-COM0031 and 20-COM0032.
Detailed Construction Schedule
9/19/22 – 12/31/22
• Finish gravel plant equipment installation
• Finalize gravel plant utilities
• Finalize site grading
• Finalize onsite entrance road grading and preparation
• Install misc. yard equipment
• Continue work on inside batch plant equipment and utilities
• Finish office spaces in batch plant
• Begin testing and calibration of all equipment
• Begin and finish drainage and utility work on CR 54G to prepare for road improvements
1/1/23 – 3/1/23
• Begin CR 54G paving and improvements – estimated finish in spring of 2023
• Pave onsite entrance road
• Finalize all onsite miscellaneous equipment installation and testing
Due to economic impacts, material shortages and road improvement schedule, offsite hauling has been delayed until early 2023.
*subject to change as project progresses.
Detailed meeting information is below
When: Thursday, December 29, 2022 @ 6pm
Where: 2711 N Overland Trail, Laporte, CO 80535
Click the links below for Previous Meeting details and literature
https://www.lrmconcrete.com/wp-content/uploads/2023/01/Presentation_2022_Q4.pdf
https://www.lrmconcrete.com/wp-content/uploads/2023/01/Presentation_2022_Q3.pdf
https://www.lrmconcrete.com/wp-content/uploads/2023/01/Presentation_2022_Q2.pdf
https://www.lrmconcrete.com/wp-content/uploads/2023/01/Presentation_2020_Q1.pdf
https://www.lrmconcrete.com/wp-content/uploads/2023/01/Presentation_2019_Q4.pdf
https://www.lrmconcrete.com/wp-content/uploads/2023/01/Presentation_2019_Q3.pdf
https://www.lrmconcrete.com/wp-content/uploads/2023/01/Presentation_2019_Q2.pdf
Questions? Comments? Contact us directly at LaporteComments@LRMconcrete.com