Construction Schedule
UPDATE: Beginning April 2022 Loveland Ready Mix Concrete will continue onsite construction operations under Development Construction Permit 20-DCP0005.
Construction activities for the Permit will consist of clearing and grubbing existing vegetation from the construction site, construction of the perimeter berms, access roads, ditch crossings; rough grading of the batch plant area and construction of the water management pond; erection of the batch plant and supporting building and facilities; finish grading, install concrete, asphalt, sod, seeding and general landscaping.
Quarterly Briefings will resume. Detailed meeting information is below the updated construction schedule.
Updated Construction Schedule
4/18/22 – 6/18/22
- Inspect and if needed repair Erosion Control Plan components
- Finish digging retention/detention ponds
- Utilities installation
- Run electrical, natural gas and water into site
- Finish Berm installation
- Finish Grading of batch plant area
- Install gravel plant components
- Finish Assembly of Batch Plant
- Utilities install for batch plant building
- Natural gas
- Electrical
- Septic
- Potable water
- Complete misc. yard equipment set up
- Finish concrete installation in cold storage building
6/18/22 – 8/1/22
- Finish concrete installation for batch plant buildings
- Construct batch plant building
- Construct cold storage building
- Landscape Installation
- CO RD 54G improvements (notification of exact schedule to be sent to neighbors prior)
- Final touches to prepare for operation
*subject to change as project progresses
Laporte Quarterly Briefing
When: May 2nd, 2022 @ 6pm
Where: 2711 N Overland Trail, Laporte, CO 80535
Pamphlet:
Click the links below for Previous Meeting details and literature
Click below to View the Landscape Plan
Questions? Comments? Contact us directly at LaporteComments@LRMconcrete.com